What should I do if the lawn has not been mowed by the end of the mowing schedule? Or if the mowing has been completed before the end of the schedule?

Updated on 2026/01/28
(1) The default schedule settings are:
① When the mowing time reaches the end time, the task will automatically conclude;
- If you wish for GOAT to complete the entire mowing area, you can enable the “Extend” switch in the schedule. Once enabled, if GOAT fails to complete the task within the preset time, it will prioritize resuming the unfinished task during the next permitted mowing window. (Enabling this switch will disable the trim schedule.)
- Adjust schedule times based on actual conditions.
② Weekly cycle: All schedules reset at midnight every Sunday, restarting with new tasks the following week.
- Adjust schedule times based on actual conditions.
(2) If a full mow cycle completes before the scheduled end time, GOAT will finish early and resume mowing at the next scheduled start time.